IE11 Not Supported

For optimal browsing, we recommend Chrome, Firefox or Safari browsers.

Texas Approves New ERCOT Process to Speed Data Center Grid Connections

What to Know:
  • The Public Utility Commission has approved a new ERCOT process to sort through more than 438,000 megawatts of large-load interconnection requests.
  • Projects will face higher requirements as ERCOT works to identify legitimate demand and determine where transmission upgrades may be needed.
  • ERCOT will notify developers in the first study group, known as batch zero, in August.

BIZ-ERCOT-WARNS-RISING-TEMPERATURES-MAY-1-DA.jpg
The Margaret Hunt Hill Bridge is seen behind high transmission power lines running along Interstate 35E and the Trinity River in Dallas, on Feb. 12.
Tom Fox/TNS
Tribune News Service — Data centers and other large electricity users wanting to connect to the Texas electric grid soon will be freed from the holding pattern many have faced as a massive number of requests has clogged the approval process.

The Public Utility Commission approved a plan that aims to streamline the procedure for more than 438,000 megawatts of large load requests — with 89 percent being data centers — waiting to plug into the grid. The Electric Reliability Council of Texas (ERCOT) created the new system to sift through the exploding volume of data centers requesting interconnection and determine how many of the projects are legitimate.

The proposed projects will now need to meet higher requirements, such as showing they have the land and financing necessary to begin building.

“Texas is experiencing an energy transformation unlike anything we have seen before,” ERCOT President and CEO Pablo Vegas said. “This new process represents a fundamental shift in how ERCOT manages the significant growth of large load interconnection, providing a structured, transparent path forward that protects reliability for Texans while supporting the state’s continued economic growth.”

ERCOT’s long-term load forecast has ballooned because of the boom in requests, pushing its prediction of electricity demand to quadruple by 2032, though officials have said those predictions are inflated by requests that may be speculative.

Under the new study process, ERCOT will group large projects into a single study, or batch, to speed up the evaluation process, remove speculative projects and identify what new transmission infrastructure may be required to serve them.

The Data Center Coalition helped push for the refined batch study process.

“Some data center projects have met all necessary requirements and have been awaiting interconnection for years,” said Cameron Poursoltan, senior manager of energy policy in Texas for the coalition.

The new framework also includes provisions for large electric users bringing their own generation, which diminishes the strain on the grid, and creates options for those that agree to allow ERCOT to curtail their power use when demand is high.

The full-picture understanding of true demand should allow for a better allocation of grid capacity and help the grid operator identify where transmission upgrades are truly needed.

“The response from the Texas energy community was remarkable,” said Jeff Billo, ERCOT vice president of interconnection and grid analysis. “The depth of participation and quality of feedback were extraordinary, and both directly shaped how ERCOT manages large load connections.”

Developers of the first group of projects to be studied, known as “batch zero,” will be notified in August. Applications to be in the secondary group for interconnection, dubbed batch one, will open next summer.

©2026 the San Antonio Express-News. Distributed by Tribune Content Agency, LLC.